ABBOTSFORD CHRISTIAN SCHOOL Heart. Mind. Soul.

THIS SQUARE INCH BUILDING PROJECT

Our world belongs to God. Every square inch of it!

In the grand scheme of things, Abbotsford Christian School is but one square inch of this world, however it is a place that is near and dear to our hearts. After all, we entrust ACS with the education and formation of our children.

From the beginning, Abbotsford Christian has been committed to Christ-centered, innovative education—many call us innovative thought leaders. We continue to aspire to deliver education that prepares students to shape God’s world in a rapidly changing global community.

God is doing great things at and through ACS. In the spirit of our forward-looking, entrepreneurial forefathers, we continue to think of and plan for the future.

To find out more about the TSI Building Project, select a topic in the menu above or read one of our most recent updates below. 

Oct5, 2021

TSI Building Project Update: October 2021

September 2021 featured many new and exciting milestones for grades 5-12 students and staff to use for their learning. They came back to a school that looked drastically different from what they left in June just a few months previous. Thanks to significant renovations of current spaces, many of the older spaces look and feel brand new! Overall, the TSI Building Project continues to march forward towards the ultimate goal of completion. WHAT'S HAPPENED: [...]

Jun2, 2021

TSI Building Project Update: June 2021

OPENING OF SECONDARY WEST WING: On Friday, May 21 we received a partial occupancy permit for the new secondary west wing. This is very exciting! On Tuesday, May 25 the students and staff participated in a COVID friendly commissioning. Attaining this permit is actually ahead of schedule—a testament to Fricia’s construction management team; they have done an incredible job coordinating this wing and the entire project. Students and staff are now busy moving into these [...]

May5, 2021

TSI Building Project Update: May 2021

WHAT’S HAPPENED: There are three main sections of the project that are considered “new build” and each of them are at different stages. We also have additional areas we are renovating. In total, the five main sections are: In the middle school wing, we are occupying this space and loving it! Currently our grade 7 and 8 classes are in this wing. Just last week, we added decals and artwork to the walls allowing this space to [...]

Apr7, 2021

TSI Building Project Update: April 2021

It’s April! Spring is in full swing, and so is our TSI construction project. The project itself continues to move forward, but there are some additional things happening behind the scenes which are also exciting! Many of you received a hard hat tour (those of you who have chosen to participate in the TSI campaign).   What's Happened: There are three main sections of the project that are considered “new build” and each of [...]

Feb2, 2021

TSI Building Project Update: February 2021

It’s February, and it’s time for another TSI Monthly Update. The construction itself continues to move forward, but there are some new and exciting things happening behind the scenes!  WHAT’S HAPPENED: There are three main sections of the project that are considered “new build” and each of them are at different stages. We also have additional areas we are renovating. In the middle school wing, we are now in the final occupancy permit stage of the project. [...]

Jan5, 2021

TSI Building Project Update: January 2021

Happy New Year! With the much-anticipated welcoming of 2021, we also welcome the ongoing excitement and momentum of the TSI Building Project! At this point, the project is more than 60% complete and many of the portions of the project are shaping up very nicely. The Lord continues to bless our community with this project, and we are very excited to be able to share the progress. What's Happening: In terms of the actual project, [...]