THIS SQUARE INCH BUILDING PROJECT

BUILDING PROJECT TIMELINE

2019
March 18

MIDDLE SCHOOL & LEARNING COMMONS ADDITION

Two more portables installed on tennis courts – March 2019

Middle School Gym Addition – occupancy expected September 1, 2019

Middle School Six Classroom and Music Room Addition – occupancy expected December 31, 2019

Library and Office Addition – occupancy expected August 2020

April 4

GROUND BREAKING CELEBRATION

Details coming soon

July 1

SECONDARY CLASSROOM ADDITION

Construction on the secondary campuses eight classroom addition – occupancy expected August 2020.

2020
January 1

SECONDARY SCHOOL RENOVATION

Renovation on the remaining areas of the secondary school are expected to begin in early 2020.

July 1

SCIENCE WING & LSS

Science Wing Demolition – occupancy expected August 2020

Learning Support Services Renovation – occupancy expected August 2020